Type of Property:5 bed house
Work Undertaken:Fitted new bathroom, including:
  • New shower cubicle with rain shower head and separate handspray kit and triple thermostatic shower valve
  • New tiles throughout, including all walls, floor and side of bath
  • New basin and WC, complete with new boxing, tiled throughout, with access panel above cistern
  • New ceiling lights
  • New bath taps and shower mixer
  • Regrouted tiles in 2 other bathrooms
  • Deep cleaned entire house
Time Taken:2.5 weeks
Problems Encountered during the project:The floor was on quite a significant slope, so we had to compensate by building up the floor level on one side of the bathroom to ensure the floor was level but this meant the floor in the landing was then lower, so this was then built up with new thick underlay and a good quality, thick carpet.
Approximate Cost:£7,000